Boundary Trials Railway has scheduled repairs to the Railway Crossing on PTH#3 west of COOP. 

The road closure is planned for 18:00 Hrs on Jul 21, reopening ASAP (hopefully within 12-16 hours). The detailed work plan is as below:

  • July 19 Monday: Foreman inspect the area and unload material

  • July 20 Tuesday: Build panel

  • July 21 Wednesday (evening): install crossing

  • July 22 Thursday: clean up the site and demob

The detour going west will be Mountain Street to Rd14N to Rd 30W and PTH#3. Detour coming from West to Morden will be PTH#3 to RD 30 W to Mountain Street to PTH#3.

UPDATE: Local traffic on PTH#3 on either side of the railway crossing between Mountain street and Rd30W will be allowed, however, the crossing will be closed to traffic.

UPDATE 2: The sidewalk crossing will be closed as well.