Boundary Trials Railway has scheduled repairs to the Railway Crossing on PTH#3 west of COOP.
The road closure is planned for 18:00 Hrs on Jul 21, reopening ASAP (hopefully within 12-16 hours). The detailed work plan is as below:
July 19 Monday: Foreman inspect the area and unload material
July 20 Tuesday: Build panel
July 21 Wednesday (evening): install crossing
July 22 Thursday: clean up the site and demob
The detour going west will be Mountain Street to Rd14N to Rd 30W and PTH#3. Detour coming from West to Morden will be PTH#3 to RD 30 W to Mountain Street to PTH#3.
UPDATE: Local traffic on PTH#3 on either side of the railway crossing between Mountain street and Rd30W will be allowed, however, the crossing will be closed to traffic.
UPDATE 2: The sidewalk crossing will be closed as well.
Traffic Detour Plan
Project Contact
Travis Long
General Manager
Boundary Trail Railway Company Inc.
Office: 204-242-2051
Cell: 204-242-4201